How Long Does a Kitchen Remodel Take in Boca Raton? A Realistic Timeline from a Local GC

If you’re planning a kitchen remodel in Boca Raton or anywhere in Palm Beach County, the honest answer is this: a full kitchen renovation — from the first design conversation to the final walk-through — typically takes between 14 and 22 weeks from start to finish. That includes planning, permitting, ordering materials, and the actual construction. The construction phase alone, once your permits are approved and your cabinets are on-site, usually runs 6 to 10 weeks depending on scope. If someone is quoting you four weeks flat on a full gut job, ask them to walk you through exactly how that works — because in South Florida, the permitting process alone can eat up three to six of those weeks.

We’ve been doing this since 1992, and the number one thing that catches homeowners off guard isn’t the construction — it’s everything that happens before the first cabinet goes up. Let’s break it down phase by phase so you know what you’re actually signing up for.

Phase 1: Planning and Design (Weeks 1–4)

Before a single permit gets pulled, you need a plan. That means finalizing your layout, selecting materials, and locking in your scope of work. This phase takes longer than most people expect — usually three to four weeks — because the decisions you make here ripple through everything else.

Are you moving the sink? That affects plumbing rough-in. Are you relocating the range? That may require new gas lines or a dedicated 240V circuit. Are you opening a wall to the dining room? That might require a structural engineer’s sign-off before the city will accept your permit application.

In a design-build approach, your contractor and designer are working from the same set of plans, which compresses this phase and avoids the back-and-forth that happens when you hire them separately. If you’re working in an established neighborhood like St. Andrews or Boca West, your HOA may also have an architectural review process that adds time — usually two to four weeks on top of city permitting.

Phase 2: Permitting in Palm Beach County (Weeks 3–8)

This is where South Florida is different from most of the country, and it’s the phase most contractors either gloss over or don’t mention at all.

Any kitchen remodel involving electrical, plumbing, structural changes, or mechanical work in Palm Beach County requires a permit. Period. That’s not optional, and it’s not something a good contractor will try to work around. Florida building codes — especially post-Hurricane Andrew and the updates that followed — are strict for a reason. You’re in a coastal climate with real hurricane exposure, and the inspectors take that seriously.

Permit review timelines in Boca Raton and surrounding municipalities typically run two to six weeks, depending on the complexity of your project and the current backlog at the city building department. Projects involving structural changes (load-bearing walls, beam installation) or new MEP (mechanical, electrical, plumbing) rough-ins go through plan review, which takes longer than a standard over-the-counter permit.

Your contractor should be managing this process, tracking status, and following up — not leaving you to wonder where things stand. If you’re getting vague answers about permitting timelines, that’s a red flag.

Phase 3: Material Lead Times — The Hidden Schedule Risk

This is the gap that competitor content almost never addresses honestly, and it’s the one that causes the most frustration among homeowners we work with.

Custom cabinetry — the kind you’d choose for a Boca Raton or Highland Beach kitchen that’s actually going to hold up and look right — typically has a 6 to 12 week lead time from the factory. Semi-custom runs 4 to 8 weeks. Stock cabinets from a big box store can arrive in days, but they’re not what you’re after if you’re doing a real renovation.

Countertop fabrication in quartz or natural stone (marble, granite) adds another 2 to 4 weeks after cabinet installation, since the template can’t be taken until cabinets are set and level. Specialty appliances — think commercial-style ranges, panel-ready refrigerators, or integrated dishwashers — can run 8 to 16 weeks, especially if they’re coming from European manufacturers.

The bottom line: a contractor who doesn’t order materials until after permits are approved is adding 6 to 12 weeks of unnecessary wait time to your project. A good GC overlaps these processes — submitting for permits and placing material orders simultaneously, so everything is staged and ready the day the permit is in hand.

Phase 4: Demolition and Rough-In (Weeks 8–11)

Once permits are approved and materials are staged, demolition moves fast — usually two to three days for a standard kitchen gut. What follows is the rough-in phase: framing any new walls, rough plumbing, rough electrical, and HVAC modifications if needed. Each of these trades requires an inspection before walls close, which adds scheduled hold points to the timeline.

In older Delray Beach and Boynton Beach homes — particularly anything built before 1990 — you may encounter surprises once walls open: outdated wiring (aluminum wiring was common), cast iron drain lines that need replacement, or mold behind water-damaged drywall. A licensed GC will document this, get it into a change order, and keep the project moving. An unlicensed crew or a GC without good subcontractor relationships will stall.

Phase 5: Cabinet Installation Through Final Finishes (Weeks 11–18)

Cabinet installation typically takes three to five days. After that comes countertop templating, a two-to-four-week fabrication window, and then final installation. Tile backsplash, fixture rough-in, appliance installation, hardware, and touch-up painting fill in around these milestones.

Final inspections — electrical, plumbing, and building — happen in this window. In Palm Beach County, scheduling inspections usually takes two to five business days. A well-organized GC has these requested in advance so the inspector shows up the day after work is complete, not a week later.

For homeowners near Deerfield Beach or working on seasonal properties, timing this phase to avoid the peak snowbird window (January through April) can make scheduling trades easier and reduce competition for subcontractor availability.

What Actually Delays Kitchen Remodels in South Florida

Based on 30-plus years of jobs across Palm Beach County, here’s what actually pushes timelines out:

  • Late material selections — Every week you take to pick your countertop is a week added to your schedule
  • Change orders mid-construction — Moving a wall after permits are issued means revised plans, re-inspection, and lost schedule
  • Permit delays — Projects with incomplete drawings or missing engineering documents go to the back of the review queue
  • Subcontractor availability — Especially during South Florida’s busy winter season, trades book up fast
  • Hidden conditions — Mold, water damage, and outdated systems discovered after demo can add one to three weeks depending on scope

A contractor who builds float time into your schedule and communicates proactively when something shifts is worth more than one who promises a tight deadline and then goes quiet. You should be getting regular updates — not chasing someone down for answers. Learn more about how we manage projects from start to finish on our general contractor services page.

Frequently Asked Questions

Do I need a permit for a kitchen remodel in Boca Raton?

Yes, if your project involves any electrical, plumbing, mechanical, or structural work — which most full kitchen remodels do — you’ll need a permit from the City of Boca Raton Building Division. Cosmetic-only work (painting, hardware swaps, minor fixture replacements) may not require a permit, but anything that touches systems or structure does.

Can I live in my home during a kitchen remodel?

Most homeowners do stay in their homes, but you’ll be without a functioning kitchen for the majority of the construction phase. Setting up a temporary kitchen (microwave, mini fridge, electric skillet) on a different floor makes it workable. If you’re in a smaller home or have young children, some families prefer to relocate for the core construction weeks.

What’s the difference between a 10-week and a 16-week kitchen remodel timeline?

Scope and material lead times are the main drivers. A cosmetic remodel — new cabinets, countertops, and appliances in the existing footprint with no structural or MEP changes — typically runs 10 to 13 weeks total. A full gut with layout reconfiguration, custom cabinetry, structural changes, and high-end appliances with long lead times will push into the 16-to-22-week range.

How does hurricane season affect my kitchen remodel timeline in South Florida?

Hurricane season (June through November) doesn’t typically stop interior kitchen remodels, but it can slow material deliveries and affect subcontractor scheduling if a named storm approaches. Projects involving exterior work — windows, doors, or roofing tied to a kitchen addition — may face weather-related delays. We account for this in scheduling and keep you informed.

Should I hire a design-build firm or manage my own subs for a kitchen remodel?

For most homeowners, design-build is the lower-risk path. You have one point of contact, one contract, and one team accountable for the entire outcome. Self-managing subcontractors works if you have construction experience and significant time to devote — but coordinating plumbers, electricians, tile setters, and cabinet installers around inspection windows is a full-time job during the project.

Ready to Get a Real Timeline for Your Kitchen Remodel?

If you’re planning a kitchen renovation in Boca Raton, Delray Beach, Boynton Beach, or anywhere in Palm Beach County, the best thing you can do right now is get on a call with someone who can walk through your specific scope and give you an honest projection — not a number pulled from thin air to win the job.

KMR Enterprises has been building and remodeling homes across South Florida since 1992. We pull our own permits, manage our own subcontractors, and give you a single point of contact from design through final inspection. Contact us today to schedule a free consultation and get a timeline and estimate that actually reflects your project.